Cost guide

HDB Toilet Renovation in Singapore: What It Costs per Bathroom in 2026, What a Package Covers, and Why Waterproofing Is the Line That Matters

By the Dreamakers Interior design team · Reviewed by our project management team · Published October 2026, prices checked 22 October 2026 · 9 min read
Renovated HDB toilet in a 4-room resale flat at Chai Chee with grey stone-look tiles, wood laminate vanity cabinet, white basin and mirror cabinet, by Dreamakers Interior
HDB toilet renovation in Singapore at a glance (2026)
BTO bathroom (keep HDB tiles)S$1,500 to S$4,000 per bathroom: vanity, mirror, shower screen, accessories, heater, lighting
Resale bathroom, full overhaulS$3,800 to S$7,500 per bathroom: hacking, waterproofing, retiling floor and walls, new bowl, basin, tap, shower, door
Two resale bathrooms togetherS$7,500 to S$15,000, usually a little less per bathroom than doing them separately
Premium bathroomS$7,000 to S$12,000: adds vanity cabinet, frameless glass screen, rain shower set, niche, concealed cistern
TimelineAbout 7 to 10 working days per bathroom; two bathrooms in 2 to 3 weeks when done together
HDB permitNeeded for hacking and retiling. New BTO bathroom floors cannot be hacked in the first 3 years
In a Dreamakers packageBoth bathrooms are fully included in the Resale All-In Package; BTO packages cover accessories and heater installation (see current packages)

Toilets are the smallest rooms in an HDB flat and, square foot for square foot, the most expensive to renovate. They are also the rooms where a cheap job goes wrong in the most expensive way, because the mistake shows up as a wet patch on your neighbour's ceiling a year later. This guide covers what an HDB toilet renovation costs in Singapore in 2026, line by line, what a package does and does not cover, the HDB rules that apply, how long the work takes, and the one line in the quote we would never let a client cut.

The short answer

Renovating an HDB toilet in Singapore costs about S$1,500 to S$4,000 per bathroom in a new BTO flat where the tiles stay, and S$3,800 to S$7,500 per bathroom for a full resale overhaul with hacking, waterproofing, retiling and new fittings. Doing both bathrooms together typically lands at S$7,500 to S$15,000. Each bathroom takes about 7 to 10 working days, and any hacking or retiling needs an HDB permit.

How much does an HDB toilet renovation cost in Singapore in 2026?

Three things set the price of a bathroom: whether the tiles come off, what goes back on the walls and floor, and the grade of the fittings. The flat type matters less than people expect, because a 3-room and a 5-room flat have bathrooms of roughly the same size. Here are the ranges we see across our own quotations in 2026:

Bathroom typeTypical scopeTypical cost per bathroom (2026)
BTO, tiles keptVanity or basin cabinet, mirror, shower screen, accessories, instant heater, lighting. HDB's tiles, bowl and basin stay.S$1,500 to S$4,000
Resale, standard overhaulHack tiles and fittings, waterproof, retile floor and walls to ceiling, new bowl, basin, tap, shower set, bi-fold door, accessoriesS$3,800 to S$7,500
Resale, premiumAs above plus vanity cabinet with stone top, frameless tempered glass screen, rain shower, tiled niche, concealed cistern or wall-hung bowlS$7,000 to S$12,000
Two resale bathrooms togetherStandard overhaul of master and common bathroom in one projectS$7,500 to S$15,000

If the bathrooms are part of a bigger project, our 4-room resale renovation guide shows where they sit inside a whole-flat budget, and the free renovation cost calculator gives an itemised range for your own flat in under two minutes.

Cost breakdown: the line items per bathroom

The ranges above come from our own client quotations, not from internet averages. When we lined up the bathroom lines across eight recent quotations in July 2026, a full retile of one HDB bathroom came in at about S$3,600 to S$3,800 before fittings, and the biggest difference between a cheap-looking quote and a complete one was whether waterproofing had its own line. Here is what a complete quote for one resale bathroom contains:

Line itemWhat it coversTypical range
Hacking and disposalRemoving floor and wall tiles, the old bowl, basin and fittings, haulage of debrisS$400 to S$900
WaterproofingMembrane over the whole floor and up the walls, then a flood testS$250 to S$600
Floor and wall tilingHomogeneous floor tiles, wall tiles to ceiling height, labour and materialsS$1,600 to S$3,200
PlumbingStainless steel pipes, inlet and outlet for basin and bowl, heater pipingS$350 to S$900
Sanitary wareToilet bowl, basin and tap, supply and installS$350 to S$1,500
Shower setMixer and hand shower, or rain shower columnS$120 to S$800
Shower screen or doorAluminium-frame bi-fold door at the low end, frameless tempered glass at the high endS$350 to S$1,200
Vanity cabinetOptional. Laminate carcass with stone or solid-surface topS$600 to S$1,500
Accessories and heaterTowel rail, paper holder, hooks, instant heater installationS$120 to S$400
ElectricalHeater point, lighting point, exhaust fan point by a licensed electrical workerS$120 to S$400

Add the low ends and you get about S$3,700 for a standard bathroom without a vanity; add the high ends with the vanity and frameless screen and you reach about S$11,000. That is the whole spread between a sensible resale bathroom and a premium one, and tiling is the biggest single line in both. Choosing a mid-range homogeneous tile rather than a large-format imported one is the decision that moves a bathroom quote more than any fitting.

Resale HDB bathroom at Serangoon Central with white marble-look wall tiles, rose gold rain shower column and matching towel hook, by Dreamakers Interior
Serangoon Central, 5-room resale. Marble-look tiles to the ceiling and a rose gold rain shower: a standard overhaul with one upgraded fitting.

Why waterproofing is the line that matters

If you only check one line on a toilet renovation quote, make it this one. When floor tiles are hacked in an HDB bathroom, the waterproofing layer underneath is destroyed with them. It has to be rebuilt before the new tiles go down: a membrane over the whole floor, turned up the walls, then a flood test where the floor is filled with water and left for a day or two to prove nothing is getting through.

Skip it, or let someone do it badly, and the bathroom looks perfect on handover day. The problem appears months later as a damp patch on the ceiling of the flat below, and at that point the only fix is to hack the new tiles out and start again. HDB treats a leak into the unit below as the responsibility of both flats to resolve, and the renovation that caused it is on you.

That is why we would rather a client cut the rain shower, the vanity or the imported tile than the waterproofing. It is also why "tiling" and "waterproofing" should be separate lines on your quote. When they are rolled into one number, you cannot see whether the second one is actually there.

What a toilet renovation package covers

Dreamakers Interior does not sell a stand-alone toilet package, and we are upfront about why: a bathroom price only means something once we have seen whether the floor needs hacking, and two bathrooms in the same flat are cheaper to do together than apart. Instead, bathrooms are built into the flat packages, and a bathroom-only job is quoted line by line using the same items as above.

  • Resale All-In Package. Both bathrooms are fully included: hacking of floor and wall tiles in the master and common bathroom, waterproofing membrane in both, homogeneous floor tiles and wall tiles to ceiling height in both, stainless steel water pipes, inlet and outlet pipes for the basins, installation of the basins, taps and sitting bowls, aluminium-frame acrylic bi-fold doors for both bathrooms, and re-wiring. Package prices are by flat type and are listed on the promotions page.
  • BTO Move-In and BTO Premium packages. HDB hands over BTO bathrooms tiled and fitted, so the packages cover what a new flat actually needs: installation of bathroom accessories and the instant heater in both bathrooms, with the kitchen and painting. A vanity cabinet or shower screen is added as a line item if you want one.
  • Kitchen and two toilets together. This is the most common partial-renovation request in resale flats, and it is quoted as one combined itemised scope rather than a bundle. The saving is real: hacking, waterproofing and tiling crews come to site once, and the debris goes out in one haulage.

Whatever the package, every bathroom line is itemised before you sign. If a bathroom quote you are comparing is a single number, ask for the lines.

Want a number for your own bathrooms?
Get an instant, itemised cost range based on our recent client quotations. Free, under two minutes.
Use the free reno calculator →

Do you need an HDB permit to renovate a toilet?

Yes, for anything that touches the tiles. The rules that apply to almost every HDB bathroom job:

  • Hacking and retiling need a permit. Removing or replacing floor or wall tiles in a bathroom is permit work, applied for by an HDB-licensed renovation contractor before hacking starts. Replacing the bowl, basin, taps, accessories or a shower screen on existing tiles does not.
  • New BTO bathrooms: no floor hacking for three years. HDB does not allow the floor tiles in the bathrooms of a new flat to be replaced during the first three years after completion, to protect the waterproofing it installed. You can overlay or change fittings, but not hack the floor. This is the main reason BTO bathroom budgets are so much lower than resale ones.
  • Waterproofing when the floor is replaced. Whenever bathroom floor tiles are replaced, a new waterproofing membrane must be laid. It is an HDB requirement, not an optional extra.
  • Licensed trades. Plumbing is done by a licensed plumber and electrical points by a licensed electrical worker, and both appear as lines on the quote.
  • Working hours. Hacking and other noisy works are limited to weekdays 9am to 5pm, with no renovation on Sundays and public holidays.

The rules above are a summary of HDB's renovation guidelines, which change from time to time. Your renovation contractor is responsible for applying them to your flat, and for the permit.

Condo bathroom at The Eden with beige large-format stone-look tiles, frameless glass shower screen, rain shower and a built-in tiled shelf, by Dreamakers Interior
The Eden, condo. Large-format tiles, a frameless screen and a tiled ledge: the premium end of the spread.

How long does a toilet renovation take?

One resale bathroom takes about 7 to 10 working days from hacking to handover, and the sequence cannot be rushed because two of the steps involve waiting:

  1. Hacking and disposal, one day.
  2. Waterproofing, one day to apply, then one to two days for the flood test. This is the wait that cheap jobs skip.
  3. Tiling, three to four days for floor and walls to ceiling height, then grouting.
  4. Plumbing, fittings and electrical, one to two days for the bowl, basin, taps, shower, heater and lights.
  5. Screen, accessories and cleaning, the last day.

Two bathrooms done together take about 2 to 3 weeks, not double, because the crews move from one to the other while the first is curing. If you are living in the flat during the work, ask for the bathrooms to be done one after the other so you always have one working toilet. It adds a few days and removes a great deal of stress.

One toilet or two?

The question we are asked most about resale bathrooms is whether to renovate both or save money by doing one. Our honest answer:

  • If both bathrooms are the original 20-year-old fit-out, do both. The waterproofing in the untouched one is the same age as the one you are replacing, and a second mobilisation later costs more than doing it now.
  • If one bathroom was redone by the previous owner in the last five to eight years and the tiles are sound, keep it. Change the fittings and accessories so it matches, and put the money into the one that needs it.
  • If the budget only stretches to one, do the common bathroom. It is the one guests see and the one that usually takes the heavier use.

Bathroom ideas from real Singapore homes

Each of these is from a home we completed, with a note on what it adds to the quote.

1. Tiles to the ceiling, one material

Running the same large-format stone-look tile from floor to ceiling makes a small HDB bathroom read as one calm box instead of a patchwork. It is the standard spec in our resale package, so it costs nothing extra over a half-height wall.

2. A tiled niche instead of a plastic shelf

A recess cut into the shower wall and tiled to match holds bottles out of sight. It is a small masonry and tiling line, decided before tiling starts, and it is the detail every visitor notices.

Resale HDB shower at Anchorvale Link with wood-look plank tiles, a tiled niche for bottles, rain shower column and frosted glass screen, by Dreamakers Interior
Anchorvale Link, 5-room resale. Wood-look plank tiles with a tiled niche and a frosted screen.

3. One upgraded fitting

A rain shower column in rose gold, matte black or brushed brass, with the towel rail and tap to match, changes the feel of a standard bathroom for a few hundred dollars. Pick one finish and repeat it; mixing chrome and black is the mistake we see most.

4. A vanity cabinet with the basin on top

A laminate cabinet with a stone or solid-surface top and a countertop basin gives you storage, a surface, and a cleaner look than a pedestal basin. It is the most common upgrade in our bathroom quotes, and it is the vanity line in the table above.

5. Dark and dramatic in the master, light in the common

Because the master bathroom is private, it can take a darker scheme: charcoal tiles, black fittings, a lit mirror. Keep the common bathroom light so it feels bigger to guests. The cost is the same; it is a tile choice.

Dark master bathroom in a 4-room resale flat at 332 Hougang with a black double vanity, two stone countertop basins, backlit mirror and concrete-look floor tiles, by Dreamakers Interior
332 Hougang, 4-room resale. A dark master bathroom with a double vanity and a lit mirror.

6. A frameless screen where the bi-fold door used to be

Swapping the standard aluminium bi-fold door for a fixed frameless tempered glass panel opens the room up visually and is easier to keep clean. It is the single line that moves a standard bathroom toward the premium range, so decide early whether it is worth it to you.

More bathrooms, with the rest of each home, are in our completed projects.

How to compare toilet renovation quotes

Bathroom quotes in Singapore vary more than any other room, and the gap is almost always missing lines rather than cheaper work. Check for these before comparing totals:

  • Waterproofing as its own line, with a flood test mentioned.
  • Hacking and disposal including haulage, not "by owner".
  • Tiles to ceiling height stated, and the tile grade or allowance per square foot.
  • Plumbing with stainless steel pipes named, and who the licensed plumber is.
  • Sanitary ware with brands or an allowance, so "toilet bowl" is not the cheapest one in the catalogue.
  • Shower screen specified as bi-fold or frameless, since the price difference is three to four times.
  • Electrical points for the heater, light and exhaust fan.
  • Cleaning, site protection and GST at the end.

If a quote is a single number with "toilet" next to it, ask for the lines. Our guide on common renovation mistakes covers what else goes wrong when quotes are compared on the total alone, and our electrical and plumbing checklist lists the points to decide before the tiles go on.

The bottom line

An HDB toilet renovation in Singapore costs about S$1,500 to S$4,000 per bathroom when the tiles stay and S$3,800 to S$7,500 when they come off, takes 7 to 10 working days per bathroom, and needs an HDB permit the moment a tile is touched. Spend on the waterproofing and the tiles, pick one fitting to upgrade, and get every line in writing. The bathroom that is done properly is the one you never think about again, which is exactly the point.

Planning a toilet or bathroom renovation?

Book a free consultation and bring your floor plan. We will tell you whether the floor needs hacking, show you the bathroom in 3D with your tiles, and give you an itemised quote with every line above. No obligation.

Book a free consultation

How these figures were put together. Cost ranges come from Dreamakers Interior client quotations issued in 2026 for HDB and condo bathrooms in Singapore, rounded into ranges; package inclusions are as listed on our promotions page on 22 October 2026; HDB rules are summarised from HDB's published renovation guidelines. Every bathroom pictured is a completed Dreamakers Interior project, photographed after handover.

Frequently asked questions

How much does it cost to renovate an HDB toilet in Singapore?

In 2026, renovating an HDB toilet costs about S$1,500 to S$4,000 per bathroom in a new BTO flat where the tiles stay and only fittings, a vanity, a screen and accessories are added, and S$3,800 to S$7,500 per bathroom for a full resale overhaul with hacking, waterproofing, retiling and new sanitary ware, based on Dreamakers Interior client quotations. Two resale bathrooms done together typically cost S$7,500 to S$15,000, and a premium bathroom with a vanity, frameless screen and rain shower runs S$7,000 to S$12,000.

What does an HDB toilet renovation package include?

In the Dreamakers Interior Resale All-In Package, both bathrooms are fully included: hacking of floor and wall tiles, waterproofing membrane, homogeneous floor tiles and wall tiles to ceiling height, stainless steel water pipes, inlet and outlet pipes for the basins, installation of basins, taps and sitting bowls, aluminium-frame bi-fold doors for both bathrooms, and re-wiring, with a 5-year workmanship warranty. BTO packages cover bathroom accessories and instant heater installation, since HDB hands over BTO bathrooms already tiled. Dreamakers does not sell a stand-alone toilet package; a bathroom-only job is quoted line by line.

How long does a toilet renovation take?

A full HDB toilet renovation takes about 7 to 10 working days per bathroom: one day of hacking, one day of waterproofing plus one to two days for the flood test, three to four days of tiling and grouting, one to two days for plumbing, fittings and electrical, and a final day for the screen, accessories and cleaning. Two bathrooms done together take about 2 to 3 weeks. Dreamakers Interior issues a dated schedule with the itemised quotation.

Do I need an HDB permit to renovate my toilet?

Yes if any tiles are hacked or replaced. Removing or replacing bathroom floor or wall tiles needs an HDB renovation permit, applied for by an HDB-licensed renovation contractor before work starts, and a new waterproofing membrane must be laid whenever the floor tiles are replaced. Replacing the bowl, basin, taps, accessories or a shower screen on existing tiles does not need a permit. In a new BTO flat, HDB does not allow the bathroom floor tiles to be hacked during the first three years after completion. Dreamakers Interior is an HDB-licensed renovation contractor and handles the application.

Should I renovate one toilet or both?

If both bathrooms are the original fit-out of a resale flat, renovate both together: the waterproofing in the untouched bathroom is the same age as the one being replaced, and a second mobilisation later costs more than doing it now, which is why two bathrooms together cost S$7,500 to S$15,000 rather than double the single price. If one bathroom was redone in the last five to eight years and its tiles are sound, keep it and refresh the fittings. If only one fits the budget, Dreamakers Interior usually advises doing the common bathroom first, since it is the one guests see and the one that takes the heavier use.

Can a toilet renovation fix a leak into the flat below?

Usually yes, because a ceiling leak in the flat below almost always means the waterproofing under your bathroom floor has failed, and the only proper repair is to hack the floor tiles, lay a new waterproofing membrane, flood test it and retile. Patching grout or sealant over the tiles rarely holds. HDB treats a leak between floors as the responsibility of both flats to resolve, so a bathroom renovation done with a properly tested membrane is both the repair and the prevention. Dreamakers Interior lists waterproofing and the flood test as their own lines on every bathroom quotation.